myGC PORTAL DIRECTORY CALENDARS CAMPUSES DEPARTMENTS TAX OFFICE
Education Service Center Phase 1 main lobby.
Education Service Center Phase 1 Special Education cubicle offices.
Education Service Center Fitness Center Restroom
Education Service Center Wellness Center-Painting is underway
Demolition and abatement of rear medical building is in progress.
Metal framing and gypsum install is completed at the 2nd floor. Ceiling grid installation is underway.
Education Service Center Phase 1- Floors are being prepped for vinyl flooring and millwork installation is underway.
Education Service Center Phase 1- Terrazzo flooring installation is being finalized, final interior painting yet to be complete.
Aerial view of site work underway.
Rough grading throughout entire site.
E.F. Green 1st concrete pour on 7-10-20.
E.F. Green Aerial view of site: Parking lot poured, concrete prep work underway for bus and parent lanes
E.F. Green Junior School-Foundation footing installation underway, and underground plumbing system in progress.
E.F. Green concrete and structural steel at academic building.
E.F. Green grade beam installation at Fine Arts/Athletics building.
E.F. Green parking lots and drives substantially complete.
E.F. Green structural steel continues at academic building.
E.F. Green Mechanical Ducts Installed
E.F. Green Plumbing Top-Out Progresses Student Restrooms
E.F. Green Beam Signing
E.F. Green Signed Beam Installed
E.F. Green JS installation of interior frames is underway
E.F. Green Junior School exterior frames and sheathing progress
Elementary #17 building pad installation is complete
Lee HS Auditorium- Rigging system currently being demolished
Lee HS Auditorium-Ticket booth framed out and new terrazzo floor installed
San Jacinto Replacement-Building pad installation is complete
Excavation of new detention pond is complete.
Aerial view of new queuing lane. (Caldwell St.)
Site Improvement-Baytown J.S. Queueing Lane and Parking
SCTHS Phase 3- New Greenhouse
SCTHS Phase 3 Overhead electrical work.
Exterior of Automotive Academies Building is complete.
Installation of new grease trap is underway.
SCTHS Phase 3- Cafeteria Renovations
SCTHS Phase IV First Floor Plan Design Progress
SCTHS Phase IV Second Floor Plan Design Progress
SCTHS Phase IV Exterior Rendering- Design Progress
SCTHS Phase IV Night Rendering-Design Progress
SCTHS Phase 3 New cafeteria dining area
SCTHS Phase 3 New computer lab in the West Building
Stuart CTHS Phase 3 Cafe/Commons area.
Stuart CTHS Phase 3 cafeteria.
Stuart CTHS Phase 3 computer lab.
Stuart CTHS Phase 3 Green House.
Stuart CTHS Phase 3 Transportation Academies Building; Auto Technology.
Stuart CTHS Phase 3 Veterinary Tech Lab.
Stuart CTHS Phase 4-Building pad installation complete
Stuart CTHS Phase 4-Underground site utility work is underway
Copyright © 2016 - Goose Creek Consolidated Independent School District
powered by ezTaskTitanium TM