Facilities Planning and Construction

2019 Bond

Press the enter key or spacebar to expand or collapse the accordion

Press the enter key or spacebar to expand or collapse the accordion

Press the enter key or spacebar to expand or collapse the accordion

Press the enter key or spacebar to expand or collapse the accordion

Press the enter key or spacebar to expand or collapse the accordion

Press the enter key or spacebar to expand or collapse the accordion

Press the enter key or spacebar to expand or collapse the accordion

    • Baytown JS-Installation of cap sheet almost completed

    • Gentry JS-Installation of cap sheet almost completed

Press the enter key or spacebar to expand or collapse the accordion

    • Education Service Center Phase 1 main lobby.

    • Education Service Center Phase 1 Special Education cubicle offices.

    • Education Service Center Fitness Center Restroom

    • Education Service Center Wellness Center-Painting is underway

    • Demolition and abatement of rear medical building is in progress.

    • Metal framing and gypsum install is completed at the 2nd floor. Ceiling grid installation is underway.

    • Education Service Center Phase 1- Floors are being prepped for vinyl flooring and millwork installation is underway.

    • Education Service Center Phase 1- Terrazzo flooring installation is being finalized, final interior painting yet to be complete.

Press the enter key or spacebar to expand or collapse the accordion

    • Education Service Center Phase 2-Concrete Placement of Grade Beams

    • Education Service Center Phase 2-Sanitary Plumbing Rough-in underway

Press the enter key or spacebar to expand or collapse the accordion

    • Aerial view of site work underway.

    • Rough grading throughout entire site.

    • E.F. Green 1st concrete pour on 7-10-20.

    • E.F. Green Aerial view of site: Parking lot poured, concrete prep work underway for bus and parent lanes

    • E.F. Green Junior School-Foundation footing installation underway, and underground plumbing system in progress.

    • E.F. Green concrete and structural steel at academic building.

    • E.F. Green grade beam installation at Fine Arts/Athletics building.

    • E.F. Green parking lots and drives substantially complete.

    • E.F. Green structural steel continues at academic building.

    • E.F. Green Mechanical Ducts Installed

    • E.F. Green Plumbing Top-Out Progresses Student Restrooms

    • E.F. Green Beam Signing

    • E.F. Green Signed Beam Installed

    • E.F. Green JS installation of interior frames is underway

    • E.F. Green Junior School exterior frames and sheathing progress

    • E.F. Green Aerial View- lightweight concrete poured at rooftop

    • E.F. Green Installation of sheathing and waterproofing progresses

    • E.F. Green Interior metal framing continues in Building A & B

    • E.F. Green MEP systems progress on second floor

    • E.F. Green masonry installation at academic wings.

    • E.F. Green sheathing installation at Fine Arts building.

    • E.F. Green gypsum board installation progresses along corridor.

    • E.F. Green MEP systems progresses at Athletics and Fine Arts Bldg.

    • E.F. Green Junior School overall aerial view of site.

    • E.F. Green Junior School shotput and discus platform

    • E.F. Green Junior School metal panel installation at building perimeter.

    • E.F. Green Junior School millwork installation in classrooms.

    • E.F. Green Junior School-Grading and forming for sidewalks

    • E.F. Green Junior School-Box culverts tied into Harris Co. detention pond

Press the enter key or spacebar to expand or collapse the accordion

    • GCCISD ES No. 17-Building pad installation is complete

    • GCCISD ES No. 17 Final grading underway in preparation of concrete pour at parking lot

    • GCCISD ES No. 17- Plumbing rough-in underway throughout entire building pad

    • GCCISD E.S. no. 17 concrete pad and driveway nearly complete.

    • GCCISD Elementary #17 overall aerial view of site

    • GCCISD Elementary #17 domestic water line and fire line vault and meter box

    • Jessie Lee Pumphrey Elementary clerestory framing at collaborative area.

    • Jessie Lee Pumphrey Elementary lightweight concrete installation at roof.

    • Jessie Lee Pumphrey ES- Brick installation complete at building

    • Jessie Lee Pumphrey ES- Metal panels scheduled to be installed in October

    • Jessie Lee Pumphrey ES- Ceramic tile installation underway in corridors

    • Jessie Lee Pumphrey ES-Millwork installation underway in the classrooms

    • Jessie Lee Pumphrey ES-Accent painting progressing at Media Center

    • Jessie Lee Pumphrey ES- Aerial view of campus

    • Jessie Lee Pumphrey ES-Millwork installed in teacher workroom

    • Jessie Lee Pumphrey ES-Plumbing fixtures being installed in restrooms

    • Jessie Lee Pumphrey-Carpet installation complete at gym

    • Jessie Lee Pumphrey-Flooring and wall graphic installation

    • Jessie Lee Pumphrey-Early Learning Academy Exhibit installation nearly complete

    • Jessie Lee Pumphrey ES-Project is substantially complete, GC working on punchlist items

Press the enter key or spacebar to expand or collapse the accordion

    • Lee High School-Armstrong Auditorium-Rigging system currently being demolished

    • Lee High School-Armstrong Auditorium-Ticket booth framed out and new terrazzo floor installed

    • Lee High School-Armstrong Auditorium-Gypsum installation nearly complete in lobby area

    • Lee High School-Armstrong Auditorium-Tile installation complete in restroom

    • Lee HS new ceiling and sprinkler system installed throughout.

Press the enter key or spacebar to expand or collapse the accordion

    • Gentry JS Fine Arts-Soil compacting nearly complete at new parking lot

    • Lee HS Fine Arts-Building pad being prepared for select fill

    • Gentry JS Fine Arts-New parking lot and detention pond expansion

    • Lee HS Fine Arts-Stormwater, water, and sewer installation

    • Gentry JS Fine Arts-Demolition of interior spaces complete, plumbing rough-in is underway

    • Lee HS Fine Arts- Drilled piers placement underway

    • Gentry JS Fine Arts-New Band Hall Space

    • Lee HS Fine Arts-Structural steel being erected

    • Gentry JS Fine Arts-Orchestra Hall is substantially completed

    • Lee HS Fine Arts-MEP systems top-out is underway

    • Lee HS Fine Arts-MEP systems top-out continues

    • Lee HS Fine Arts-Exterior sheathing installation is underway at the Band Hall area

    • Lee HS Fine Arts-Gypsum board taping and floating is ongoing

    • Lee HS Fine Arts-Tile has been installed at first floor restrooms

Press the enter key or spacebar to expand or collapse the accordion

    • San Jacinto Replacement-Building pad installation is complete

    • San Jacinto ES- Moisture barrier installed in preparation of concrete pour at Area D of building pad

    • San Jacinto ES- Plumbing rough-in underway throughout entire building pad

    • San Jacinto Elementary Replacement overall aerial view of site

    • San Jacinto Elementary Replacement structural steel of main entry of building

    • San Jacinto Elementary Replacement metal decking installation

    • San Jacinto Elementary joist installation at first floor near entrance.

    • San Jacinto Elementary parent drive poured near front entry.

    • San Jacinto ES-Aerial View-Roof ready for lightweight concrete

    • San Jacinto ES- Brick installation progresses at East side of building

    • San Jacinto ES-Rigid insulation underway at West side of building

    • San Jacinto ES-Gypsum installation continues in corridors

    • San Jacinto ES-Millwork installation underway in the classrooms

    • San Jacinto ES-Decorative light fixtures installed at commons area

    • San Jacinto ES-Masonry installation underway at building entrance

    • San Jacinto ES-Kitchen equipment installation is underway

    • San Jacinto ES-Storefront glazing system installation nearly complete

    • San Jacinto ES-Flooring and wall graphic installation

    • San Jacinto ES-Terrazzo flooring installation at rotunda

    • San Jacinto ES- Early Learning Academy Exhibit installation nearly complete

    • San Jacinto ES-Project is substantially complete, GC working on punchlist items

Press the enter key or spacebar to expand or collapse the accordion

      • Excavation of new detention pond is complete.

      • Aerial view of new queuing lane. (Caldwell St.)

      • Site Improvement-Baytown J.S. Queueing Lane and Parking

    Press the enter key or spacebar to expand or collapse the accordion

Press the enter key or spacebar to expand or collapse the accordion

    • Stallworth Stadium Fieldhouse-Aerial View-Building Pad

    • Stallworth Stadium Field House-CMU Block Installation

Press the enter key or spacebar to expand or collapse the accordion

    • Sterling HS MEP Package #1-Fire sprinkler line installation continues in hallways

    • Sterling HS MEP Package #1- Insulation of ductwork continues in classrooms

    • Sterling HS MEP Package #1-Exisisting conduit supported in corridor

    • Sterling HS MEP Package #1-Wall demolished in women's restroom

    • Sterling HS MEP Package #1- Cement board installed in restrooms

    • Sterling HS MEP Package #1- Ductwork tied into VAV boxes

    • Sterling HS MEP Package #1-Fixtures and partitions installed in restrooms

    • Sterling HS MEP Package #1-Final cleaning complete in classrooms

    • Sterling HS MEP Package #1-Installation of Air Handling Unit E1

    • Sterling HS MEP Package #1-Sanitary and Vent Piping a 2nd Floor Restroom

    • Sterling HS MEP Package #1-Ceiling grid installation in corridor

    • Sterling HS MEP Package #1-Medium pressure ductwork installation in Bio/Chem lab

    • Sterling HS MEP-Abatement and demolition of ductwork

    • Sterling HS MEP-Demolition of Air Handler Unit

    • Sterling HS MEP Package #1-Hard ceiling installation is underway in classrooms

    • Sterling HS MEP Package #1-Ceramic tile installation nearly complete in restrooms

    • Sterling HS MEP #1-Sprinkler heads and speaker installation underway at band hall

    • Sterling HS MEP #1-Toilet partitions installation complete in restrooms

Press the enter key or spacebar to expand or collapse the accordion

    • Junior School Running Tracks-Gentry JS-Rough grading of running track

    • Junior School Running Tracks-Horace Mann JS-Rough grading of track

    • Junior School Running Tracks-Gentry JS- Concrete curb placement underway.

    • Highlands JS framing for concrete curbs.

    • Gentry JS synthetic track surface.

    • Baytown JS-track grading completed

    • Highland JS-Track grading completed

    • Junior School Running Tracks-Baytown JS-Asphalt base complete

    • Baytown JS Running Tracks- Track surface painted

Press the enter key or spacebar to expand or collapse the accordion

    • SCTHS Phase 3- New Greenhouse

    • SCTHS Phase 3 Overhead electrical work.

    • Exterior of Automotive Academies Building is complete.

    • Installation of new grease trap is underway.

    • SCTHS Phase 3- Cafeteria Renovations

    • SCTHS Phase IV First Floor Plan Design Progress

    • SCTHS Phase IV Second Floor Plan Design Progress

    • SCTHS Phase IV Exterior Rendering- Design Progress

    • SCTHS Phase IV Night Rendering-Design Progress

    • SCTHS Phase 3 New cafeteria dining area

    • SCTHS Phase 3 New computer lab in the West Building

    • Stuart CTHS Phase 3 Cafe/Commons area.

    • Stuart CTHS Phase 3 cafeteria.

    • Stuart CTHS Phase 3 computer lab.

    • Stuart CTHS Phase 3 Green House.

    • Stuart CTHS Phase 3 Transportation Academies Building; Auto Technology.

    • Stuart CTHS Phase 3 Veterinary Tech Lab.

    • Stuart CTHS Phase 4-Building pad installation complete

    • Stuart CTHS Phase 4-Underground site utility work is underway

    • SCTHS Phase 4-Aerial View-new concrete driveway poured; perimeter grade beams complete

    • Stuart CTHS Phase 4 mechanical, electrical, and plumbing top-out continues at first and second level

    • Stuart CTHS Phase 4 overall aerial view of site plan

    • Stuart Career Tech HS P4 brick installation at south wall.

    • Stuart Career Tech HS P4 framing at second floor atrium.

Press the enter key or spacebar to expand or collapse the accordion

  • 0:00 / 0:00

Press the enter key or spacebar to expand or collapse the accordion

  • 0:00 / 0:00

Press the enter key or spacebar to expand or collapse the accordion

  • 0:00 / 0:00

Press the enter key or spacebar to expand or collapse the accordion

  • 0:00 / 0:00

Press the enter key or spacebar to expand or collapse the accordion

  • 0:00 / 0:00

Press the enter key or spacebar to expand or collapse the accordion

  • 0:00 / 0:00

Press the enter key or spacebar to expand or collapse the accordion

Press ENTER key to focus on the active panel
    • Technology Center Expansion-Front Facade-Waterproofing

    • Technology Center Expansion-Interior workspace-MEP systems

Press the enter key or spacebar to expand or collapse the accordion